Jump to content
Microsoft Windows Bulletin Board

Recommended Posts

Posted

Hi!

Most probably this might not be possible in MS Project / Project Online, but it doesn’t hurt to check with the Project Community.

We have a task assigned to two resources, and the Project Manager's idea is that either of these two resources can complete the whole task to 100%, not only their 50% of it.

We have tried various combinations of Fixed Duration / Work / Units with and without Effort Driven but haven’t found any combination that works so one of the two resources can complete the task to 100%. It always ends up being half. For example, the resource goes to My Tasks and submits 80%, but in the project, it shows 40%.

We have also looked into using the Team Resource option, but it requires the resources to take an extra step, assigning the task from the Team to themselves, which is not what we are looking for.

Does this requirement have any solution, or should we stop investigating and give up?

Thank you.

View the full article

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...